Title: Vote on a request by Lee Bowman, Project Manager, on behalf of NNP Briar Chapel, LLC for subdivision Preliminary Plat approval of Briar Chapel, Phase 13 - Sections 1 & 2, consisting of 43 lots on 11.03 acres, located off SR-1532, Mann's Chapel Road, and Great Ridge Parkway, parcel #'s 80418, 86285, and 2617
Attachments: 1. More Information from Planning Board Website
TITLE
Vote on a request by Lee Bowman, Project Manager, on behalf of NNP Briar Chapel, LLC for subdivision Preliminary Plat approval of Briar Chapel, Phase 13 - Sections 1 & 2, consisting of 43 lots on 11.03 acres, located off SR-1532, Mann's Chapel Road, and Great Ridge Parkway, parcel #'s 80418, 86285, and 2617
ABSTRACT
Action Requested:
Vote on a request by Lee Bowman, Project Manager, on behalf of NNP Briar Chapel, LLC for subdivision Preliminary Plat approval of Briar Chapel, Phase 13 - Sections 1 & 2, consisting of 43 lots on 11.03 acres, located off SR-1532, Mann's Chapel Road, and Great Ridge Parkway, parcel #'s 80418, 86285, and 2617
Introduction & Background:
Zoning: Conditional Use District / Compact Community
Water System: Public, Chatham County
Sewer System: Private wastewater treatment plant
Subject to 100 year flood: Zone X
General Information: Compact Community approved in 2005 for 2,389 dwelling units on 1,589 acres, permit revised in 2012, 2014, and 2017. Current number of dwelling units allowed based on the 2017 CUP amendment is 2650.
Reviewed: Under pre-2008 Subdivision Regulations

Discussion & Analysis:
The request before the Board is for subdivision preliminary plat review and approval of Briar Chapel, Phase 13, Sections 1 & 2 consisting of 43 lots on 11.03 acres.
Roadways: The lots will be accessed by private alleyways off Great Ridge Parkway. Although the lots are accessed by private alleyways, NCDOT reviewed the road plans for Phase 13, Sections 1 & 2 due to driveway connections and drainage. Great Ridge Parkway received final plat approval as part of Briar Chapel, Phases 3 & 4, and Great Ridge Parkway right-of-way dedication plat in 2007. The road plan for Great Ridge Parkway was reviewed and approved by NCDOT in April, 2007 prior to preliminary plat approval. A financial guarantee is in place for the completion of construction of Great Ridge Parkway and this financial guarantee is in the process of being increased to refl...