Title: Receive a request from the Board of Education for a vote to approve the purchase price of the elementary school site.
Attachments: 1. Proposed Site - Andrews Store and Parker Herndon Roads

Title

Receive a request from the Board of Education for a vote to approve the purchase price of the elementary school site.

 

Abstract

 

Introduction & Background:

 

NC General Statute 115C-426(f) requires that the board of education receive board of commissioners’ approval on the purchase price of property.

 

The Board of Education has gone through an extensive process to identify and select a suitable site for the new elementary school.

 

The Board of Education has selected property on Andrew’s Store Road at the southwest corner of the intersection of Parker Herndon Road.  A plat of the property is attached.

 

To date, the Board of Education has performed the following site investigations of the property:

Administrative

                     Preliminary review with Chatham County Planning indicates that the project will require a conditional use permit revision to the Briar Chapel C.U.P.

Design

                     Architect has determined that a one-story 750 capacity elementary school physically fits on the site.

                     Preliminary siting provides for one point of entrance on Parker Herndon Road. 

Utilities

                     Municipal water is in close proximity

                     Briar Chapel’s wastewater treatment facility is in close proximity

Traffic Impact Analysis

                     Recommended Improvements 

                     Andrews Store Road

o                     Widen to three lanes from Granite Mill Blvd to Woodland Grove lane with appropriate turn lanes for Woodland Grove and Parker Herdon. 

                     Parker-Herndon

o                     Install turn lanes into site and onto Andrews Store Road

o                     Install signal at Andrews Store/Parker Herndon

 

The closing date is projected to be during or prior to September of 2017.

 

Discussion & Analysis:

 

The board of education is requesting approval of the purchase price for the following property:

                     Parcel # 0079946 (23.46 acres): Owned by Briar Chapel

                     Parcel # 0002715 Windsor Parcel (2.05 acres) Owned by Briar Chapel

                     Total acreage: 25.51 acres

                     Total Cost: $750,000.00 plus closing costs

 

 

Budgetary Impact:

 

The recommended 2018-2024 CIP includes $750,000 for an elementary school.

 

Recommendation: Approve the purchase price for parcels 79946 and 2715 in the amount of $750,000.00 plus closing costs.