Title
Vote on a request to Approve a Change Order for the Recycling Station Contract and allow the County Manager to execute the Change Order
Abstract
Action Requested: Approve the Change Order to the Contract
Introduction & Background: A Contract was awarded to Simpson Contractors for the construction of a Recycling Station for the conversion to single stream recycling. Do to site conditions encountered during construction, additional work is necessary to complete the site work.
Discussion & Analysis: The additional work is needed to complete construction.
Budgetary Impact: The Change Order is for $4,802.64.
Recommendation: Approve the Change Order.