Legislation Details

File #: 13-0284    Version:
Type: Agenda Item Status: Approval of Agenda and Consent Agenda
File created: 3/5/2013 In control: County Manager's Office
On agenda: 3/11/2013 Final action:
Title: Award bids for Annex renovations to Bordeaux Construction and amend the Annex Project Budget to reflect increased cost
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
Title
Award bids for Annex renovations to Bordeaux Construction and amend the Annex Project Budget to reflect increased cost
Body
Bids were received on February 6 to renovate the eastern half of the Annex Building. Sixteen bids were received. Bordeaux Construction was the low bidder, as follows:
Base bid: $1,181,999
Alternate 1 (replace windows): $37,700
Alternate 2 (owner preferred security system): $0
Alternate 3 (new window blinds): $1,900
Alternate 4 (new coating on exterior corridors): $7,200
Alternate 6 (framing in attic spaces): $2,000
Alternate 7 (add structural reinforcement to elevated floor slab): $7,300
Total: $1,238,099
 
The bid with selected alternates exceeds the current budget by $88,349. In addition, structural work needed in the design phase has added $6,000 to the design budget. Staff has worked to trim the furnishings budget by $10,000. Overall the project is over budget by $84,349, as shown in the table below:
 
Current Budget
Revised Budget
Difference
                  1,149,750.00
                                      1,238,099.00
                        88,349.00
                      126,400.00
                                         132,400.00
                          6,000.00
                      114,975.00
                                         104,975.00
                      (10,000.00)
                      114,975.00
                                         114,975.00
                                       -   
                  1,506,100.00
                                      1,590,449.00
                        84,349.00
 
Staff recommends that the bid be awarded and the project budget amendment as shown above.