Title: Vote on a request by Goldston Apex Properties dba Builder's First Source - to rezone approximately 4.19 acres to be added to the current development for three new storage structures and laydown yard from Residential District (R1) to Conditional District Light Industrial (CD-IL) and to reclassify the existing zoning of Conditional Use Light Industrial District (CU-IL) to Conditional District Light Industrial (CD-IL), including all or a portion of parcels 17893 and 73463.
Attachments: 1. More Information from Planning Department website
TITLE
Vote on a request by Goldston Apex Properties dba Builder's First Source - to rezone approximately 4.19 acres to be added to the current development for three new storage structures and laydown yard from Residential District (R1) to Conditional District Light Industrial (CD-IL) and to reclassify the existing zoning of Conditional Use Light Industrial District (CU-IL) to Conditional District Light Industrial (CD-IL), including all or a portion of parcels 17893 and 73463.
ABSTRACT

Action Requested:
Request by Goldston Apex Properties dba Builder's First Source - to rezone approximately 4.19 acres to be added to the current development for three new storage structures and laydown yard from Residential District (R1) to Conditional District Light Industrial (CD-IL) and to reclassify the existing zoning of Conditional Use Light Industrial District (CU-IL) to Conditional District Light Industrial (CD-IL), including all or a portion of parcels 17893 and 73463.
Introduction & Background:
A legislative public hearing was held on June 15, 2015. The Planning Department presented the request and provided an overview. Speaking on behalf of the applicant was Karen Calloway, PE, from Mack Gay Associates, owner, Jim Goldston, and one adjacent landowner Ms. Jean Fish. No other testimony was given.

Goldston Apex Properties first located in Chatham County in 1997 with the first approval for conditional use district and a conditional use permit issued July 22nd on the 46 acre parcel with conditions which can be viewed on the Planning Department website. The business has continued to operate and expand its services to meet the growing building construction industry.
There has been one revision to the CUP to install an ATM machine that required an additional three conditions: (1) Facility to have secure surveillance cameras; (2) An alarm system be installed and maintained; and (3) The top of the structure not exceed ten (10) feet.