Title: Vote on a request to approve NNP Briar Chapel, LLC for subdivision preliminary plat approval of Boulder Point Drive Extension consisting of 3.59 acres located off Andrews Store Road, SR-1528, Baldwin Township, parcel 87024
Attachments: 1. More Information from Planning Department Website
TITLE
Vote on a request to approve NNP Briar Chapel, LLC for subdivision preliminary plat approval of Boulder Point Drive Extension consisting of 3.59 acres located off Andrews Store Road, SR-1528, Baldwin Township, parcel 87024
ABSTRACT

Action Requested:
Request by Lee Bowman, Project Manager on behalf of NNP Briar Chapel, LLC for subdivision preliminary plat approval of Boulder Point Drive Extension consisting of 3.59 acres located off Andrews Store Road, SR-1528, Baldwin Township, parcel 87024
Introduction & Background:
Zoning: Conditional Use District / Compact Community
Water System: Chatham County
Sewer System: Private Wastewater Treatment Plant
Subject to 100 year flood: No floodable area within this site request
General Information: Compact Community approved in 2005 for 2,389 dwelling units on 1,589 acres. Permit revised in 2012, and 2014 increasing the dwelling units to 2,500.
Reviewed: Under pre-2008 Subdivision Regulations

Discussion & Analysis:
Briar Chapel is requesting preliminary plat approval on a portion of Boulder Point Drive. This section provides access to the WWTP and is currently graded and the travel-way has been graveled. The developer would now like to complete the construction of the roadway to a public, NCDOT standard. This is considered infrastructure construction which requires preliminary plat approval with review and permits from other agencies. The other agency permits required for this request are:

Soil Erosion and Sedimentation Erosion Control July 8, 2015
Control Permit Permit

NCDOT Road Construction July 21, 2015

NCDENR Stormwater Plan July 10, 2015
Boulder Point Extension
There are no new utility (water / sewer) designs for this p...