Skip to main content
Launch Recite Me assistive technology
LEGISLATIVE RESEARCH CENTER
File #: 24-5410    Version: 1
Type: Contract Status: Passed
File created: 6/28/2024 In control: Public Works
On agenda: 7/15/2024 Final action: 7/15/2024
Title: Vote to approve a contract with The Wooten Company for Task Order No.1 for the Hatley Road Water Main Extension Project in the amount of $342,700.00
Indexes: Comp Plan Goal 7: Provide infrastructure to support desired development and support economic and environmental objectives.
Attachments: 1. FY25 Wooten Company Task Order 1 - Hatley Road Watermain Extension

Title

Vote to approve a contract with The Wooten Company for Task Order No.1 for the Hatley Road Water Main Extension Project in the amount of $342,700.00

 

Abstract

Introduction & Background: The County currently has over 900 homes and Seaforth High School on a single water main feed on Big Woods Road and is experiencing low water pressure at the end of the watermain on Mount Gilead Road.  The Hatley Road watermain extension will provide a second watermain feed on Big Woods Road and will substantially improve water pressure on Mount Gilead Road.  

                     

Discussion & Analysis: The County intends to extend a 12-inch water main from Calm Winds Lane west along Hatley Road to Mt. Gilead Church Road and a 16-inch water main north along Mt. Gilead Church Road from Hatley Road to just south of Sunset Grove Drive to loop the watermain on Mount Gilead Road with Big Woods Road. This “looping” will provide resiliency and improve the level of service to customers while also providing the capability to support new development. The total length of the extension is estimated to be 10,700 feet.

 

How does this relate to the Comprehensive Plan: Provides infrastructure to support future development, improves customer service and fire flows.

 

Budgetary Impact: The project is budgeted in the Capital Improvement Plan.

                     

Recommendation/Motion:  Motion to approve a contract with The Wooten Company for Task Order No.1 for the Hatley Road Water Main Extension Project in the amount of $342,700.00.