Title: An update to the Board regarding the SPOT 4.0 state transportation project submittal list for Durham-Chapel Hill Carrboro Metropolitan Planning Organization (DCHC-MPO); Vote on a request to approve an interlocal agreement for MPO membership, and an update from staff regarding the use of MPO Discretionary Funds.
Attachments: 1. Interlocal Agreement, 2. Projects 21Sept15BOC, 3. Transportation_Update_21sept15 BOC presentation
TITLE
An update to the Board regarding the SPOT 4.0 state transportation project submittal list for Durham-Chapel Hill Carrboro Metropolitan Planning Organization (DCHC-MPO); Vote on a request to approve an interlocal agreement for MPO membership, and an update from staff regarding the use of MPO Discretionary Funds.
ABSTRACT

Action Requested:
An update to the Board regarding the SPOT 4.0 state transportation project submittal list for Durham-Chapel Hill Carrboro Metropolitan Planning Organization (DCHC-MPO); Vote on a request to approve an interlocal agreement for MPO membership, and an update from staff regarding the use of MPO Discretionary Funds.
Introduction & Background:

The purpose of this update is to provide the Board with information on the submitted transportation projects within the DCHC-MPO boundary for SPOT 4.0, to have a discussion regarding the use of MPO discretionary funds and to authorize the County Manager to sign the City of Durham and Chatham County Inter-local Cooperation Agreement Local Match for the Durham-Chapel Hill-Carrboro Metropolitan Planning Organization (DHCHC-MPO) Federal Transportation Grants.

Discussion & Analysis:

SPOT 4.0
Staff has worked with NCDOT to identify projects eligible for the statewide transportation project ranking process known as SPOT 4.0. The County was only eligible to submit bicycle/pedestrian projects, and intersections projects within the DCHC-MPO boundary of the County. This is because Chatham County has no highway improvements identified on the MPO's long-range plan. The MPO did allow Chatham County to submit O'Kelly Chapel Road for operational improvements, which could include safety improvements if deemed necessary by NCDOT. Please refer to the attached list for all Chatham projects being submitted through the MPO.

Discretionary Funds
Staff will provide an update to the Board regarding the status of the MPO discretionary funds useable for non-highway projects within the MPO boundar...