TITLE
Vote on a request to approve Contentnea Creek Development Co., for a twenty-four (24 month) extension of the validity of the preliminary plat approval for the Cooper Subdivision to extend the preliminary plat expiration date from June 20, 2015 to June 20, 2017.
ABSTRACT
Action Requested:
Request by Karen Kemerait, Attorney-at-Law, on behalf of Contentnea Creek Development Co., for a twenty-four (24 month) extension of the validity of the preliminary plat approval for the Cooper Subdivision to extend the preliminary plat expiration date from June 20, 2015 to June 20, 2017.
Introduction & Background:
Zoning: R-2 Water system: Public / County
Watershed: WSIV-PA Sewer System: Private
Within 100 year flood: No
Reviewed: under pre-2008 Subdivision Regulations
October 16, 2006: Approval by the Board of County Commissioners to rezone 130 acres from RA-5 to RA-90 (now R-2) and for a Conditional Use RA-90 Permit for a 63 lot single family residential subdivision with site plan. There were 17 conditions of approval. See attachment # 2.
November 19, 2007: Approval by the Board of County Commissioners for subdivision preliminary plat approval for Phase I, consisting of ten (10) lots on 23 acres with revisions to the balance of the master plan (sketch design) and approval of a development schedule as follows:
Phase I - 10 lots - Prel. submitted by Oct 2007 - Complete construction +/- May, 2008
Phase II - 24 lots - Prel. approval by July 2008 - Complete construction +/- Jan, 2009
Phase III -26 lots - Prel. approval by Oct, 2008 - Complete construction +/- May, 2009
During discussion of the Phase I preliminary design request, with the Board of County
Commissioners, the developer's attorney stated that the developer had voluntarily agreed to perform an Environmental Impact Assessment on the balance of the property,
Phases II and III. This was not made a condition of approval.
May 27, 2008: Request by Karen M. Kemerait, Attorney with Blanchard...